Home / Blog / Project Tango Palm Beach County — July 15, 2026 Vote Guide
⚠️ TIME-SENSITIVE • Market Intelligence • July 15, 2026 Hearing

Project Tango: What the July 15, 2026 County Commission Vote Means for Western PBC Property Owners

Everything you need to know before the decision. What's actually proposed, what's changed, who owns what, and what the outcome means for property values in Loxahatchee, The Acreage, and the western corridor.

🚨 Hearing Date: Wednesday, July 15, 2026 at 9:30 AM

Project Tango — formally: Central Park of Commerce Center — is a proposed hyperscale AI data center campus on 202 acres in Loxahatchee. The Palm Beach County Board of County Commissioners votes July 15, 2026 at 9:30 AM. The zoning commission already recommended approval. The Commission vote is the final decision point. If you own property within 2 miles of the site, this hearing is material to your property's value and use trajectory. Brian Wilder at 561-201-4717 is tracking this and advising clients with proximity exposure.

📞 Call Brian: 561-201-4717 Free Buyer's Guide →

I'm writing this because I have clients who own property within a mile of the proposed Project Tango site, and I want them to understand the full picture before July 15. This is not a political document. I'm not telling you to support or oppose the project. I'm telling you the facts as they stand, what the outcome scenarios look like for property values, and what questions every western PBC property owner with proximity to this site should be asking right now.

What Project Tango Actually Is

Site: 202 acres on Southern Boulevard in Loxahatchee, adjacent to the FPL West County Energy Center (3,750 MW natural gas plant). The site address is within the unincorporated western PBC corridor.

Owners: Two separate entities own different portions of the 202 acres — PBA Holdings (local group, led by Enrique Tomeu) and TPA Group (Atlanta-based, operating as WPB Logistics Owner LLC). Until recently both were pursuing a unified plan. They are now pursuing separate applications.

Original proposal (December 2025): 3.7 million square feet of data center, introduced to the public when developers sought to expand existing zoning. The December introduction triggered immediate community opposition — the public did not know data centers were planned for this site.

Scaled-back PBA Holdings proposal (current): Approximately 1 million square feet of data center space. This is the application going before the County Commission on July 15.

TPA Group separate filing (April 2026): 1.3 million square feet of warehouse-to-data-center conversion, filed separately and potentially subject to administrative approval — meaning it may not require a County Commission vote. This is the development that has most alarmed opponents, as it could expand the total data center footprint beyond what the Commission votes on July 15.

The Adjacency Issues: School, Homes, and the Arden Community

Saddle View Elementary School: The proposed data center site is proximate to the newly built Saddle View Elementary School. The Palm Beach County School Board voted in early June 2026 to send a formal letter to County Commissioners requesting a halt pending a comprehensive study. School Board member Marcia Andrews, who represents the area, stated opposition to siting a data center that close to a school.

Arden community: Arden is a newer residential community directly adjacent to the proposed data center site. Residents have been among the most organized opponents, citing noise, water usage, light pollution, and industrial-scale traffic as incompatible with adjacent residential living.

Petition opposition: Multiple petitions have accumulated 8,000+ signatures. Two opposition websites (notoprojecttango.com and stopprojecttango.org) and an active Facebook group have organized the opposition effort. The community response has been unusually high relative to typical PBC zoning hearings.

The Operator Identity Question

Florida statute permits the end-user identity of a proposed facility to be shielded in zoning proceedings. The operator of Project Tango has not been publicly confirmed.

What's on the public record: Oracle co-founder Larry Ellison's family purchased Lion Country Safari 1.8 miles from the Project Tango site in November 2025. Oracle is building AI data centers across the country as part of the Project Stargate initiative. The Project Tango project manager stated at a February 2026 town hall that the end user was "not Larry Ellison" — a clarification nobody had specifically asked for at that moment.

Brian Wilder's position: the operator identity matters because it affects the long-term operational and political trajectory of the facility if approved. A facility operated by Oracle or a similar hyperscale tenant has different permanence, scale, and infrastructure demands than a speculative data center shell. The fact that the identity is shielded does not eliminate this consideration for property owners evaluating their exposure.

What Approval Looks Like for Surrounding Property Owners

If the County Commission approves the PBA Holdings application on July 15, the approved footprint is approximately 1 million square feet of data center — roughly equivalent to 18 Walmart Supercenters under a single roof in the middle of western PBC.

The operational implications for adjacent residential property: data centers generate continuous mechanical cooling noise, require significant water usage for cooling (the scale of demand has been a central community concern), draw heavy infrastructure traffic during construction and equipment delivery, and operate 24/7 with associated lighting and activity.

The TPA Group's separate 1.3M sq ft application adds up to a combined total of approximately 2.3M sq ft of data center space if both proceed — still substantially reduced from the original 3.7M sq ft proposal, but a significant industrial footprint in a corridor that is currently residential-adjacent acreage.

Property value impact: Industrial-scale data center operations adjacent to residential acreage have a documented negative effect on nearby residential property values in other markets where this has occurred. The magnitude depends heavily on proximity, orientation, and the specific operational characteristics. Properties 2+ miles from the site with no direct sight line or sound exposure are likely minimally affected. Properties within 0.5–1 mile with direct adjacency are the highest-exposure cases.

What Denial Looks Like

If the County Commission denies the PBA Holdings application, the PBA Holdings portion of Project Tango does not proceed under the proposed plan. However, the TPA Group's separate application — if determined to be administrative — could still advance without a Commission vote. Denial of one application does not automatically halt the other.

A full denial of both applications would leave the 202-acre site with its existing approved uses — warehouse and light industrial — which are less intensive than hyperscale data center operations but are not residential uses.

Brian Wilder's honest note: A clean denial that eliminates all data center risk for this site is the best possible outcome for nearby residential property owners. A partial outcome — Commission denial followed by TPA administrative approval — may provide partial relief but not full elimination of the data center scenario.

If You Own Property in the Western Corridor Right Now

  • Within 0.5 miles of the site: The July 15 outcome is directly material. Brian Wilder is advising clients with this exposure on both hold and exit scenarios.
  • 0.5–2 miles from the site: The outcome affects your market more than it affects your specific property. Monitor the July 15 result and the 90-day price data that follows.
  • 2+ miles from the site: The data center story is context for your market, not a direct valuation driver. The western corridor's underlying fundamentals — no HOA, real land, Lake Okeechobee access — are unchanged.
  • Buyers currently under contract on western PBC property: Verify your property's specific distance from the Project Tango site. If within 1 mile, understand the July 15 outcome and its implications before your inspection contingency period closes.

Questions About Your Specific Property?

Brian Wilder is tracking the July 15 hearing and will update clients with western PBC exposure immediately after the vote. If you own property in Loxahatchee, The Acreage, or the western corridor and want to understand your specific exposure, call before the hearing.

Call: 561-201-4717

Spanish-speaking property owners: 561-285-8809 — Lucy López

Frequently Asked Questions

What is Project Tango in Palm Beach County?+
Project Tango is the code name for the Central Park of Commerce Center, a proposed hyperscale AI data center campus on 202 acres in Loxahatchee, Palm Beach County. Originally proposed at 3.7 million square feet, it was scaled back to approximately 1 million square feet (PBA Holdings portion) after significant community opposition in December 2025. The Palm Beach County Commission votes on the application July 15, 2026 at 9:30 AM.
Where exactly is Project Tango located?+
The 202-acre Project Tango site is located in unincorporated Loxahatchee along Southern Boulevard in western Palm Beach County. It is adjacent to the FPL West County Energy Center, approximately 1.8 miles from Lion Country Safari, and proximate to the Arden residential community and the new Saddle View Elementary School.
Who owns Project Tango?+
Two entities own different portions of the 202-acre site: PBA Holdings (a local group led by Enrique Tomeu) and TPA Group (an Atlanta-based company operating as WPB Logistics Owner LLC). The end-user operator identity has not been publicly confirmed — Florida statute permits this information to be shielded in zoning proceedings.
When is the Project Tango vote?+
The Palm Beach County Board of County Commissioners votes on the PBA Holdings application Wednesday, July 15, 2026 at 9:30 AM. This is the final decision point — the zoning commission already recommended approval, and the County Commission vote is the last opportunity for public input and binding decision.
Will Project Tango affect property values in Loxahatchee?+
Properties within 0.5–1 mile of the site with direct adjacency face the highest exposure. Properties 2+ miles away are likely minimally affected. The July 15 outcome, and the 90-day price data following that outcome, will be the clearest real-time read on the market's actual reaction. Brian Wilder at 561-201-4717 is tracking this and can assess the specific implications for any western PBC address.

Brian Wilder
Wilder Real Estate Group at Keller Williams Wellington
561-201-4717 · In business since 1996 · 1,500+ transactions in Palm Beach County

All facts sourced from county records, verified news sources, and public filings as of June 2026. Hearing date subject to change — confirm at pbcgov.org before attending. This post does not constitute legal or regulatory advice. Equal Housing Opportunity.