Project Tango Goes to a Vote July 15. Here's What's Actually on the Table.
1.8 million square feet of data center proposed. Roughly 1 million survived the fight. But total construction on the 202 acres barely shrank — the warehouses grew to cover the difference. On July 15, Palm Beach County votes on which number it was supposed to notice.
Wednesday, July 15, 2026, 9:30 AM, the County Commission holds the final zoning hearing on Project Tango — the Central Park of Commerce Center, 202 acres on Southern Boulevard at 20-Mile Bend, about 1.8 miles from Lion Country Safari. After six months of opposition, the developer cut the data center from 1.8M to ~1,032,000 sq ft and doubled the setback from Arden and Saddle View Elementary to ~2,000 feet — but the warehouses grew, so total buildout barely moved. Meanwhile a second landowner filed a rival ~1.2M-sq-ft data-center plan that may never need a public vote, and the two owners are now in court. July 15 decides one application. It may not decide the one that matters most.
On Wednesday, July 15, 2026, at 9:30 in the morning, the Palm Beach County Board of County Commissioners holds the final zoning hearing on Project Tango — formally the Central Park of Commerce Center, a 202-acre site on the north side of Southern Boulevard at 20-Mile Bend, about four miles west of Seminole Pratt Whitney Road and roughly 1.8 miles from Lion Country Safari. The original application asked for 1.8 million square feet of hyperscale AI data center plus 1.9 million square feet of warehouses — 3.7 million square feet of total buildout. After six months of organized community opposition, the developer cut the data center to about 1,032,000 square feet, doubled the distance to the Arden community and Saddle View Elementary School to roughly 2,000 feet, and committed to enclosed equipment, no diesel generators, and a closed-loop cooling system. Meanwhile, the second landowner on the same property filed a separate, rival application for roughly 1.2 million square feet of data center space — one that may be processed administratively, without a public vote — and in June took the fight to court. I'm Brian Wilder. This is the piece in my Western Palm Beach County Watchlist series with a clock on it: a date, a room, and a decision. Here's what July 15 actually decides — and what it doesn't.
How we got here — one corridor, several angles
If you've been following this series, you've watched the same corridor convert from several different angles: Larry Ellison's family buying Lion Country Safari at farmland prices, the NuRock affordable apartments going up at Southern and Seminole Pratt on land Wellington annexed, the Live Local Act giving workforce housing a path around local zoning, and the sod fields between Southern Boulevard and 20-Mile Bend losing half their muck with every harvest. Project Tango is the piece where all of it stops being a trend story and becomes a decision. Seven county commissioners, one morning in downtown West Palm Beach, one vote.
And here's the detail that connects this hearing to everything else: the applicant, PBA Holdings, is a subsidiary of Palm Beach Aggregates — the rock mine company. They bought this property in 1993, dug it for rock, converted mined-out pits into water storage reservoirs, sold a piece to Florida Power & Light for the power plant that now sits next door, and in 2014 sold the eastern section for $77 million to make way for Arden — 2,300 homes. Read that timeline again. Farm to mine to reservoir to power plant to neighborhood to data center. That is the land-conversion cycle I've described all series, on a single parcel, run by a single owner. The people fighting Project Tango from their homes in Arden are living on land the same company sold them a decade ago.
What the developer gave up — read the site plan, not the headline
In March, project manager Ernie Cox rolled out the revised plan and called it a direct response to community concerns. Here's the honest math.
What got cut: the data center footprint dropped from 1.8 million square feet to about 1,032,000 — a 43 percent reduction in the part of the project people hate. The distance from the data center buildings to the nearest Arden homes and to Saddle View Elementary roughly doubled, to about 2,000 feet — around five and a half football fields. The developer committed to enclosing the noisemaking equipment, skipping diesel generators, and cooling with a closed-loop water system that recirculates rather than consumes. The project website puts potable water use around 5,000 gallons a day; county filings have estimated total water use closer to 1.7 million gallons a month. That gap — between the developer's number and the county's — is exactly the kind of thing July 15 exists to resolve.
What didn't get cut: the warehouses grew from 1.9 million square feet to just over 2.3 million. Total construction on the site went from 3.7 million square feet to roughly 3.3 million. The developer gave up the label people were fighting and grew the category people tolerate. I've sat across the table from enough negotiators since 1996 to recognize the move. It's not dishonest — it's negotiation. But you should see it for what it is before you decide what you think of it.
What the concessions tell you: six months ago, this project was sailing toward approval with a zoning-commission recommendation in hand. Then more than 400 people packed the Royal Palm Beach Cultural Center in February and booed the project manager off the stage. The commissioners voted 7-0 in December to slow down. The April 23 vote got pushed to July 15 at the applicant's own request, through its law firm, Carlton Fields. Every delay, every redesign, every doubled setback was paid for by people in green shirts showing up. Whatever happens July 15, that part already happened — the opposition moved a billion-dollar site plan. In my years watching county zoning fights, that is rare.
The side door — the rival application almost nobody is watching
July 15 decides PBA's application. It may not decide TPA's. The front door has a vote. The side door might not.
The 202 acres has two owners. PBA Holdings controls most of it. But 60 acres in the center belong to Atlanta-based TPA Group, operating as WPB Logistics Owner LLC. The two worked together for months — then, in late April, TPA broke ranks and filed its own site plan: replacing roughly 1.2 million square feet of approved warehouse space with data center buildings, with outdoor generator yards, outdoor chillers, and a water-treatment building. In other words, the rival filing walks back the very commitments — enclosed equipment, no diesel, closed loop — that PBA made to survive the community fight. PBA's land-use attorney, Brian Seymour, publicly disavowed it: separate applicants, separate ownership, separate applications.
And here's the kicker: because TPA's filing modifies an already-approved site plan rather than requesting new zoning, it may be processed administratively — no public hearing, no commissioner vote, no green shirts in the room. As of mid-June, the dispute moved from dueling filings to open litigation: TPA's WPB Logistics sued PBA Holdings, seeking an emergency injunction to force PBA to withdraw the very master-plan application set for July 15. The suit made public a contract amendment that gave PBA the right to take back land it had agreed to sell — signed by both sides in November, then terminated by PBA in December, the day after the first hostile commission hearing. The two companies that built this project together are now fighting each other in court over who gets to cash in on it.
The wild card — the district's commissioner just did a U-turn
At the February town hall, in front of a packed and hostile room, Sara Baxter — the county mayor and the District 6 commissioner whose district includes the Tango site, along with Royal Palm Beach, Loxahatchee Groves, The Acreage, Wellington, Westlake, and the Glades — said plainly that she would not vote for Project Tango. She also spent the spring answering questions about money: a review of campaign records by WPTV found PBA Holdings donated $10,000 to her re-election fund, and The Acreage Advocate tallied $12,000 in contributions from project-linked donors. Baxter's response, on the record: donations do not dictate her votes, and she opposes the project.
Then it got strange. On June 8 she dropped her commission re-election bid and filed to run for Congress in Florida's newly redrawn 22nd Congressional District — a seat reshaped by the mid-decade redistricting the governor signed in May. Days later, after President Trump posted on Truth Social that he would rather she stay on the commission, Baxter dropped the congressional bid and re-entered the commission race. So as of this writing she is back, still in office, and on track to be one of the seven votes on July 15 — not a commissioner halfway out the door, but very likely the deciding district's voice in the room.
Which sharpens, rather than removes, the legal wrinkle the lawyers are watching: zoning hearings are quasi-judicial, and commissioners are required to come in without prejudgment. Baxter's public promise to vote no — made to applause in February — is exactly the kind of statement that reporting has flagged could get her sidelined from the proceeding under Palm Beach County case law. Sit with that: the commissioner who represents the site, who told her constituents she'd vote no, and who just chose to stay in the seat, might not be allowed to cast that vote. Whether she participates in the hearing is a live question. (This situation moved twice in June; confirm Baxter's status at the pre-publish re-check.)
Who else is lined up where
The Palm Beach County School Board voted on June 3 to send a formal letter asking commissioners to halt the project until a comprehensive study of health effects on Saddle View Elementary students, teachers, and staff is completed. School Board member Marcia Andrews, whose district covers the area, has said flatly she opposes a data center that close to a school. The opposition is organized — the Western Palm Beach County Community Alliance, the Classroom Teachers Association, Arden residents like Ben Brown who literally live next to the fence line. On the other side: the economic-development case, the FPL power plant next door that makes this site uniquely attractive to data center operators, and an end user whose identity is shielded by Florida statute — Cox has denied the rumors about Related Ross and Oracle, and as of this writing nobody has confirmed who the tenant would be. Both sides are still working.
What I tell buyers and sellers before July 15
I'm Brian Wilder, and the Wilder Real Estate Group has closed more than 1,500 transactions in Palm Beach County since 1996. Here's the judgment layer.
Who thrives here
The buyer who understands they're purchasing in a transition corridor and prices that in. Acreage and Loxahatchee land buyers with a 7-to-10-year horizon aren't threatened by this hearing either way — a data center next to a power plant at 20-Mile Bend is far from most residential parcels people actually buy.
Who regrets it
The Arden-area buyer who closed in the last two years believing the western edge of their world was permanent. The lesson for the next buyer: in this corridor, check what's already approved around you before you fall in love with the house. These warehouses were entitled before most of Arden moved in.
The hidden cost
Uncertainty itself. Until the TPA application and the lawsuit resolve, properties near this corridor carry a question mark some buyers will use as a negotiating hammer. Selling near Arden or western Southern this summer? Your pricing has to account for headline risk, not just comps.
The honest alternative
If industrial-scale neighbors are a dealbreaker, the answer isn't to wait out one vote — it's to buy where the land use is already settled: a gated community with the rules locked in, or acreage far enough from the conversion corridor that the 10-year picture is quieter. Rules person or freedom person? Both are valid; the wrong answer sends you to the wrong corridor.
What this story is not
- Not decided. The July 15 vote is real, and the dais itself is in motion — the district's own commissioner may or may not participate.
- Not a done deal for the opposition either. A scaled-back plan with doubled setbacks and a willing power supplier next door is a much harder application to deny than the original.
- Not one application. The TPA Group rival filing is separate, larger in some respects, may not require a public vote at all — and is now the subject of litigation between the two owners.
- Not a confirmed tenant. The end user's identity is shielded by Florida statute. The Related Ross and Oracle rumors have been denied on the record.
- Not a corruption story. The campaign contributions are reported, sourced, and on the record — and so is Commissioner Baxter's denial that they influence her vote. I report what's documented; you decide what it means.
- Not the end of the corridor story. Whatever happens July 15, the land-conversion pattern this series documents continues with or without this project.
- Not a reason to panic if you own out here. It's a reason to know exactly what's entitled around your parcel. That's a phone call, not a crisis.
Before the vote, not after
Of all the pieces in my Western PBC Watchlist, this is the one with a clock on it. If you own land out here, or you're thinking about buying or selling anywhere near Southern Boulevard west of Seminole Pratt, the time to understand your position is before July 15 — not after the headlines tell you what happened.
Call Brian Wilder: 561-201-4717 · brian@palmbeachcountyhomeforsale.com
Spanish-speaking owners: 561-285-8809 — Lucy López
Frequently Asked Questions
When is the Project Tango vote?+
What exactly is Project Tango?+
How close would the data center be to Saddle View Elementary School?+
Could part of Project Tango get built even if commissioners vote no?+
Will Commissioner Sara Baxter vote on Project Tango?+
Will Project Tango hurt home values in Arden, The Acreage, or Loxahatchee?+
Who is the data center actually for?+
How can I attend or watch the July 15 hearing?+
Brian Wilder
The Wilder Real Estate Group at Keller Williams Wellington
561-201-4717 · brian@palmbeachcountyhomeforsale.com · In business since 1996 · 1,500+ Palm Beach County transactions · 5th-generation Palm Beach County local
This article previews a public zoning hearing and reflects reporting available in mid-June 2026; it is real-estate market commentary, not legal, investment, or development advice. The hearing date, the TPA/PBA litigation, and Commissioner Baxter's candidacy status were each in motion as of publication and may change — confirm current status before acting. Square-footage and distance figures are drawn from public filings and reporting and may be refined at the hearing. Information deemed reliable but not guaranteed. Equal Housing Opportunity.
More in this series: NuRock & the Loxahatchee-Wellington corridor · Larry Ellison bought Lion Country Safari · Florida's Live Local Act